| Project | Scope of Work | Date | Location | Client | Reference |
1 | HVAC System for 13.8kV/ 33kV Sub Station SS # 7202 | Engineering, Procurement and Construction – EPC of HVAC System | Jan, 2012 | Shaqra | SEC | Mr. Kukreja (PM) gdkukreja@alojaimi.com |
2 | Fire Alarm & Fire Fighting System | Engineering, Procurement and Construction – EPC of Fire Alarm and Fire Fighting System | Mar, 2013 | Riyadh | KACST | Engr. Saad H. Alqahtani shalqhtani@kacst.edu.sa Tel.: +966-00010125 |
3 | Design of Solar Panel | Deign of Solar Panel for KACST, Energy Research Institute (ERI) | Feb 2013 | Riyadh | KACST | Engr. Saad H. Alqahtani shalqhtani@kacst.edu.sa Tel.: +966-00010125 |
4 | Maintenance of Road Blockers | Maintenance of Mechanical, Control and Hydraulic Systems of Road Blockers | Aug, 2013 | Riyadh | Deera Palace | Engr. Saeed Muhammad Shaeer saiedshaier@fgcltd.com |
5 | LV Cabling | LV Cabling between ARAMCO and SEC metering stations | May, 2012 | Riyadh | ARAMCO & SEC | |
6 | HVAC System of Palace | Modification in the existing HVAC system to resolve low CFM and high noise issues | Jan, 2013 | Riyadh | Prince Turkey Palace | |
7 | HVAC System of Palace | Major overhauling 120 tons capacity chiller, Design, install and commission the new control system for chiller | July, 2012 | Riyadh | Princess Noora Bint-e-Saad | |
8 | نظام مكافحة الحرائق | Procurement and installation of Fire Fighting System for residential Labor Complex | Sep, 2013 | Riyadh | MASIC | Engr. Rami rami@tmmep.com |
9 | Plumbing System | Installation of Gray water, water supply, rain water and treated water piping | Nov, 2013 | Riyadh | MASIC | Engr. Rami rami@tmmep.com |
10 | HVAC System for 13.8kV/ 33kV Sub Station SS # 7180 | Engineering, Procurement and Construction (EPC) of HVAC System | Jan, 2014 | Dawadmi | SEC/Al-Ojaimi | Mr. Kukreja (PM) gdkukreja@alojaimi.com |
11 | HVAC System for 132kV/ 33kV Sub Station SS # 8190 | Engineering, Procurement and Construction (EPC) of HVAC System | 2015 | Riyadh | SEC/Al-Ojaimi | Mr. Kukreja (PM) gdkukreja@alojaimi.com |
12 | HVAC System for 132kV/ 33kV Sub Station SS # 8190 | Engineering, Procurement and Construction (EPC) of HVAC System | 2015 | Riyadh | SEC/Al-Ojaimi | Mr. Kukreja (PM) gdkukreja@alojaimi.com |
13 | HVAC System for 33kV/ 13.8kV Sub Station SS # 8190 | Engineering, Procurement and Construction (EPC) of HVAC System | 2015 | Buraidah | SEC/Auva | Mr.Faheem Usman(PM) faheem.usman@auva.com.sa |
14 | Command & Control Center – HQ Building | Building Fabric and Electromechanical Works | ??? 2016 | AL-Madinah | MOI/Etesal ?? | Abu Zar 0554256661 |
15 | Command & Control Center – HQ Building | Building Fabric and Electromechanical Works | ??? 201? | AL-Qassim (Unaizah) | MOI/Etesal?? | Abu Zar 0554256661 |
16 | AL Baha University Hospital | Plumbing and Drainage System | Jan, 2017 | Al Baha | MOE | Abu Zar 0554256661 |
17 | Split AC Units in FM200 Cylinder Rooms of 380/132/13.8kV BSP # 8671 | Supply, Installation, Testing & Commissioning | Jan, 2019 | Khamis Mushayt Housing | NG (SEC)/TIT | Mr. Osman Samir osman@altoukhi.com |
18 | HVAC System for New Head Office Building-2 | Preventive and Corrective Maintenance | Oct, 2019 | Riyadh | Alfanar | Mr. Adil Murad K.aljazeerah.corp@gmail.com |